News Flash

Posted on: February 25, 2021

Water System Upgrades at 700 Block of Fourth Street

watermain pipe public works hole

WATER SYSTEM UPGRADES 
700 Blk of Fourth Street from March 1st – March 26th, 2021 
WHAT’S HAPPENING?
Water system upgrades are planned for the 700 Blk of Fourth Street. A new water main is being installed between Elwyn S...
Read on...

City Project Gallery
Posted on: November 6, 2020

Update: Watermain Extension for Selous Creek

IMG_0600

Other than minor deficiencies, Kays Road Contracting Ltd has completed the installation of 2.2km of watermain, reaching substantial completion for the Selous Creek watermain extension project. The 1100 block of Hoover Street has been repaved and areas whe...

Read on...

City Project Gallery
Posted on: October 30, 2020

Update: Watermain Extension for Selous Creek

IMG_0585

The final tie-in of the Selous watermain extension was completed on October 29 at the top of Stanley Street, and only finishing touches remain to be done, including hydroseeding scheduled for Monday, Nov 2nd. The focus, from now through mid-December is to...

Read on...

City Project Gallery
Posted on: October 23, 2020

Update: Watermain Extension for Selous Creek

October 23 2020

Installation of the watermain along the Great Northern Trail (GNT) and along the Hoover Street Right-of-Way is now complete. The final tie-in and pipe reconfiguring will take place next week (October 26-30) at the top of Stanley Street.  Hydrosee...

Read on...

City Project Gallery
Posted on: October 2, 2020

Update: Watermain Extension for Selous Creek

Over the next couple of weeks, the Kays Contracting crews will continue to work toward Mountain Station reservoir along the Hoover Street Right-of-Way. Other than the immediate residents,  little disruption is anticipated.  The works on ...

Read on...

City Project Gallery
Posted on: September 25, 2020

Update: Watermain Extension for Selous Creek

September 25 2020

From September 8th through September 18th, Kays Road Contracting Ltd. crossed the Great Northern Trail at the Hoover Street Right-of-Way (ROW) and extended the watermain along the steep slope above the old rail grade. A repetitive dull thudding sound, hea...

Read on...

City Project Gallery
Posted on: December 1, 2017

December 1, 2017 - UPDATE #10 - Hall Street Project - Phase II

10_HallStreetProgressUpdate

Click here to read the latest update on the Hall Street Project for the week of November 27th, 2017.

Read on...

City Project Gallery
Posted on: November 24, 2017

November 24, 2017 - UPDATE #9 - Hall Street Project - Phase II

9_HallStreetProgressUpdate

Click here to read the latest update on the Hall Street Project for the week of November 20th, 2017.

Placing Pipe during Phase II construction.

Read on...

City Project Gallery