Posted on: May 5, 2023
NOTICE OF WORKPHASE II - 100 BLOCK BAKER STREET WATERMAIN UPGRADESThe water utility crews from the City of Nelson will be replacing the watermain on the 100 Block of Baker Street. The work is scheduled to begin on Tuesday, May 9th and is expected to last ...
Read on...
City Project Gallery
Posted on: May 1, 2023
Pier Project update for Spring 2023
As the warm weather quickly moves in to welcome the month of May, many changes have taken place down at the waterfront.
The new pier is quickly taking shape with the floor boards being completed and the railings installed...
Read on...
City Project Gallery
Posted on: March 28, 2023
Crews have returned to the foot of Baker Street over the last few weeks and work will progress though spring and summer, with completion of the project scheduled for early fall.
Currently, the following work is underway:
Interior deck bo...
Read on...
City Project Gallery
Posted on: March 2, 2023
With our target of July 2023 in mind for the completion of the Nelson Pier project, contractors are gearing up to start work onsite at the foot of Hall Street once again.
Look for the arrival of the barge setting up alongside the pier for assista...
Read on...
City Project Gallery
Posted on: December 23, 2022
As the snow settles over the Pier worksite and we head in to the holidays, North Mountain Construction has cleaned up the worksite at the bottom of Hall Street and demobilized for a winter site closure.
While you may see some decking work still being compl...
Read on...
City Project Gallery
Posted on: October 12, 2022
You may have noticed a GWIL crane on the construction site in the last week. The crane is assisting in the install of the steel beams on the steel pilings.
MarWest recently completed the install of the storm sewer tie-in with the City storm line....
Read on...
City Project Gallery
Posted on: August 26, 2022
Here is the latest Pier Project update for the week of August 22, 2022
In early August, North Mountain Construction poured concrete in the Ladybird display building walls and strip footings.
Here is the Ladybird display building walls and footings...
Read on...
City Project Gallery
Posted on: August 5, 2022
Graham Marine continued installing the pilings. They have now demobilized from the site, leaving one barge for the welder to continue work.
The site for the Ladybird display building was prepared and the concrete footings were placed.
The rebar an...
Read on...
City Project Gallery
Posted on: June 28, 2022
Work at the pier has continued to progress steadily since the last project update. Graham Marine has finished the pier deconstruction and has removed the existing piles:
Photo showing pier deconstruction.
Photo showing pile removal.
Work has starte...
Read on...
City Project Gallery
Posted on: June 6, 2022
The project replacement project is underway with site works proceeding last week. The site and laydown area has been fenced and the work trailer is present on site. Please observe all construction signage when travelling adjacent to th...
Read on...
City Project Gallery
Posted on: May 16, 2022
Work on the Hall Street Pier Project Set to Begin
May 13, 2022
Nelson, BC - The City has been working to create opportunities to improve the current City pier, located at the foot of Hall Street and the waterfront. It was identified several years ago that t...
Read on...
City Project Gallery