Building Inspections

After a building permit is issued, several site inspections are required prior to final approval and the issuance of an occupancy permit.

A City of Nelson Building Inspector is required to do site inspections at the following stages of construction:

  1. Footings Inspection
    * Property pins or a legal surveyed plot plan required
    * On completion of form work for the footings, prior to pouring concrete
  2. Backfilling Inspection
    * On completion of damp-proofing, drain tiles and drain rock (if required), prior to backfilling
  3. Plumbing Inspection
    * Prior to covering of groundwork and above grade rough in (exfiltration test and pressure test to property line for sewer and water)
  4. Framing Inspection
    * After the entire rough-in plumbing is completed, electrical work and heating equipment is installed and the framing is completed to lockup stage, prior to insulating
  5. Fireplace Inspection
    * First inspection-installation of first flue lines above smoke chamber · Second inspection-chimney cap, but prior to installing
  6. Insulation Inspection
    * After all insulation and vapour barriers are installed but prior to covering
  7. Occupancy Inspection
    * Prior to anyone occupying any part of a building

To book an inspection, contact the Development Technician at 250-352-8260, Monday through Friday, 8:30 a.m. to 12:00 p.m. One business day notice is required for most building inspections.