News Flash

Posted on: November 2, 2018

November 2, 2018 - UPDATE #45 - Hall Street Project - Phase II

45-HallStreetProgressUpdate

Hall Street Project Update November 3 -10, 2018

As the project nears a close, both prime contractors are maintaining an eye on the weather. Both contractors are preparing for paving and sidewalk works, both critical facets of the job, requiring a weather w...

Read on...

City Project Gallery
Posted on: October 26, 2018

October 26, 2018 - UPDATE #44 - Hall Street Project Phase II

44-HallStreetProgressUpdate

Hall Street Update October 29 to Nov 3, 2018

 

The
Canadian Pacific Railway crews have completed works to upgrade both the CedarStreet and Hall Street rail crossings. The CPR works necessitated full road closures
to install large pre-cast concr...

Read on...

City Project Gallery
Posted on: October 22, 2018

October 22, 2018 - UPDATE #43 - Hall Street Project - Phase II

43-HallStreetProgressUpdate

Hall Street Update – Week of October 22nd to October 26, 2018

Monday (October 22) and Tuesday (October 23) Hall Street will be closed to through traffic because concrete panels are being installed into the CP Crossing as well as asphalt transitio...

Read on...

City Project Gallery
Posted on: October 18, 2018

Stores-To-Shores Downtown Revitalization: Hall Street Project Re-Cap

Hall Street ReCap October 2018

Stores-To-Shores Downtown Revitalization: Hall Street Project Re-Cap 

October 18, 2018

The Hall Street project addressed two important community goals: 

1) renewing end of life or inadequate infrastructure, and;

2) creating an important link...

Read on...

City Project Gallery
Posted on: October 12, 2018

October 12, 2018 - UPDATE #42 - Hall Street Project - Phase II

42-HallStreetProgressUpdate

Hall Street Update October 14 to October 20, 2018

The Canadian Pacific Railway crews are currently on site at the Cedar Street crossing preparing for full closure of the CP crossing on October 17. This work may extend into October 18; however, Hall Street,...

Read on...

City Project Gallery
Posted on: October 5, 2018

October 5, 2018 - UPDATE #41 - Hall Street Project Phase II

41-HallStreetProgressUpdate

Hall Street Update Week of Oct 8 – 12, 2018

Due to the unforeseen delay with the CP crossing, the Contractor refocused and spent this week pouring concrete in the area around the gazebo (see photo below). Landscape work has also progressed with p...

Read on...

City Project Gallery
Posted on: October 1, 2018

October 1, 2018 - UPDATE #40 - Hall Street Project Phase II

40-HallStreetProgressUpdate

Hall Street Update Week of October 1  - 5, 2018

Beginning the morning of Tuesday October 2nd, McNally will be working with CP forces to install concrete panels into the Hall Street rail crossing. These concrete panels will provide the finished sur...

Read on...

City Project Gallery
Posted on: September 25, 2018

IMPORTANT NOTICE - Hall Street Project Paving

Important Notice.pub

HALL STREET PAVING WORK WILL TAKE PLACE THIS WEEK

Paving of the 100 Block of Hall Street and the northern portion of the Hall and Front street intersection will take place between Friday, September 28th and Sunday, September 30th.

SPL (the paving contractor...

Read on...

City Project Gallery
Posted on: September 10, 2018

September 10, 2018 - UPDATE #38 - Hall Street Project - Phase II

38-HallStreetProgressUpdate

Hall Street Update Week of September 10 – 14, 2018

 

IMPORTANT UPDATE: In order to facilitate the crossing of the deep utilities in the intersection of Hall and Front streets, Marwest has scheduled this work to proceed as night work (10:0...

Read on...

City Project Gallery
Posted on: August 31, 2018

August 31, 2018 - UPDATE #37 - Hall Street Project - Phase II

37-HallStreetProgressUpdate

Hall Street Update September 4 - 7, 2018

The focus for McNally Excavating this past week has been near the gazebo, west of the Prestige. Electrical conduit and base prep was followed by the placement of concrete and sidewalk toward the end of the week. Nex...

Read on...

City Project Gallery
Posted on: August 24, 2018

August 24th, 2018 - UPDATE #36 - Hall Street Project Phase II

36-HallStreetProgressUpdate

Hall Street Update August 27 to 31, 2018

After a busy week with paving and concrete work, the contractor (McNally) has indicated he will be performing some site clean-up work on the west-side of the parking lot and then will shift focus to the area adjacen...

Read on...

City Project Gallery
Posted on: August 17, 2018

August 17th, 2018 - UPDATE #35 - Hall Street Project Phase II

35-HallStreetProgressUpdate

McNally has been busy placing fill material on the west side of the parking lot in order to obtain the grade required for concrete work and for paving. McNally has indicated that the construction of concrete formwork will proceed this Saturday for the pat...

Read on...

City Project Gallery
Posted on: August 10, 2018

August 13th, 2018 - UPDATE #34 - Hall Street Project Phase II

34-HallStreetProgressUpdate

Next week McNally is planning to pave of the
west side of the parking lot, paving the transition in the rear lane in the 100Block of Hall and paving the transition area that runs along the west side of the
100 Block of Hall, adjacent to the Taylor Wil...

Read on...

City Project Gallery
Posted on: July 27, 2018

July 27th, 2018 - UPDATE #33 - Hall Street Project Phase II

33-HallStreetProgressUpdate

Hall Street Project Update for the week of July 23 - 27th

Work on Hall Street continued to progress with the instillation of storm sewer in the 100 Block of Hall Street and the instillation of electrical conduit and light bases in the parking area adjacent...

Read on...

City Project Gallery
Posted on: July 23, 2018

July 23, 2018 - UPDATE #32 - Hall Street Project Phase II

32-HallStreetProgressUpdate

Hall Street Project Update for the Week of July 23 – 27

The City would like to remind residents that the businesses remain open and that access to Gateway Plaza and 625 Hall Street is from Lakeside Drive via the Cedar Street detour route.

The past week on t...

Read on...

City Project Gallery
Posted on: July 13, 2018

July 13, 2018 - UPDATE #31 - Hall Street Project Phase II

31 hall st

Hall Street Project Update for the Week of July 16-20th:

The past week was one of significant change along the Hall Street corridor, where long established traffic patterns, for vehicles and pedestrians alike, were altered. The traffic signals at Hall and ...

Read on...

City Project Gallery
Posted on: July 6, 2018

July 6, 2018 - UPDATE #30 - Hall Street Project - Phase II

30-HallStreetProgressUpdate

Hall Street Project Update for the Week of July 9-13th

After the long weekend, there was a flurry of activity along the Hall Street corridor. A second prime contractor, MarWest Industries Ltd., has been contracted to work uphill, south of the CP Rail track...

Read on...

City Project Gallery
Posted on: June 18, 2018

June 18, 2018 - Update #29 - Hall Street Project Phase II

29 HallStreetProgressUpdate

Hall Street Project Update for the Week of June 18 to 22nd, 2018

The City’s contractor (McNally) has completed the installation of curbs and gutters in the 100 Block of Hall Street. In the week of June 18 to 22nd, McNally will prepare this area f...

Read on...

City Project Gallery
Posted on: June 11, 2018

June 11, 2018 - Update #28 - Hall Street Project Phase II

28 hall

Hall Street Project Update for the Week of June 11-15, 2018

The City’s contractor (McNally) has been working this past week to prepare for the concrete curbing work that will proceed next week. McNally has been busy adjusting the elevation of man...

Read on...

City Project Gallery
Posted on: June 5, 2018

June 5, 2018 - Update #27 - Hall Street Project Phase II

27-HallStreetProgressUpdate

Hall Street Project Update for the Week of June 4th – 8th, 2018

The City’s contractor (McNally) has been busy this week to connect a sanitary sewer service from 625 Front Street to the new sanitary sewer piping that was installed under the CP tracks. McNal...

Read on...

City Project Gallery
Posted on: May 30, 2018

May 28, 2018 - Update #26 - Hall Street Project Phase II

26-HallStreetProgressUpdate

Hall Street Project Update – Week of May 28 to June 1, 2018

 

The Stores to Shores project on Hall Street completed a major milestone this week, with install of the deep utilities under the CPR tracks. The City contractor, McNally Excavat...

Read on...

City Project Gallery
Posted on: May 23, 2018

May 23, 2018 - Update #25 - Hall Street Project Phase II

25 Hall Street

Hall Street Project Update for the Week of May 22 - 25, 2018

Starting Tuesday of this week, the City, our contractor (McNally) and CP will install storm and sanitary piping under the CP crossing. This work will be done in conjunction with CP, as the City&a...

Read on...

City Project Gallery
Posted on: May 11, 2018

May 11, 2018 - Update #24 - Hall Street Project Phase II

24HallStreetProgressUpdate

May 11, 2018

****Be sure to visit stores on Hall Street and Lakeside Drive during construction! Our small businesses need your support.***

 

Stores-To-Shores Hall Street Project Update – Week of May 14 – 18, 2018

The City would li...

Read on...

City Project Gallery
Posted on: May 1, 2018

May 1, 2018 - Update #23 - Hall Street Project Phase II

23 HallStreetProgressUpdate

HALL STREET PROJECT - UPDATE #23 - May 1, 2018

*** ALL BUSINESSES REMAIN OPEN ON HALL STREET AND LAKESIDE DRIVE***

After a false start on Monday, crews spent Tuesday morning deploying road signs, traffic delineators and have closed the 100 Block of Hall Str...

Read on...

City Project Gallery
Posted on: April 14, 2018

April 13, 2018 - UPDATE #21 - Hall Street Project - Phase II

21-HallStreetProgressUpdate.pub

Read the latest update on the Hall Street Project for the week of April 16-20, 2018.

In Photo: Construction of concrete steps and retaining structures along the foreshore west of the Prestige Lakeside Resort. 

 

Read on...

City Project Gallery
Posted on: March 23, 2018

March 23, 2018 - UPDATE #20 - Hall Street Project - Phase II

20_hall

Read the latest update on the Hall Street Project for the week of March 26-30, 2018.

In Photo: Rendering of Future Social Steps at Waterfront Plaza

In photo: Forming of Future Social Steps

Read on...

City Project Gallery
Posted on: January 26, 2018

January 26, 2018 - UPDATE 14 - Hall Street Project - Phase II

14_HallStreetProgressUpdate

Read the latest update on the Hall Street Project for the week of January 29 - February 2, 2018.

Photo below shows the installation of two large storm manhole bases immediately adjacent Lakeside Drive.

Read on...

City Project Gallery
Posted on: January 12, 2018

January 12, 2018 - UPDATE #12 - Hall Street Project - Phase II

12-HallStreetProgressUpdate

Read the latest update on the Hall Street Project for the week of January 15-19, 2018.

In Photo - The contractor installing sanitary sewer piping to the location where a new manhole will be installed.

Read on...

City Project Gallery
Posted on: December 1, 2017

December 1, 2017 - UPDATE #10 - Hall Street Project - Phase II

10_HallStreetProgressUpdate

Click here to read the latest update on the Hall Street Project for the week of November 27th, 2017.

Read on...

City Project Gallery
Posted on: November 24, 2017

November 24, 2017 - UPDATE #9 - Hall Street Project - Phase II

9_HallStreetProgressUpdate

Click here to read the latest update on the Hall Street Project for the week of November 20th, 2017.

Placing Pipe during Phase II construction.

Read on...

City Project Gallery