News Flash

Posted on: November 6, 2020

Update: Watermain Extension for Selous Creek

IMG_0600

Other than minor deficiencies, Kays Road Contracting Ltd has completed the installation of 2.2km of watermain, reaching substantial completion for the Selous Creek watermain extension project. The 1100 block of Hoover Street has been repaved and areas whe...

Read on...

City Project Gallery
Posted on: October 30, 2020

Update: Watermain Extension for Selous Creek

IMG_0585

The final tie-in of the Selous watermain extension was completed on October 29 at the top of Stanley Street, and only finishing touches remain to be done, including hydroseeding scheduled for Monday, Nov 2nd. The focus, from now through mid-December is to...

Read on...

City Project Gallery
Posted on: October 23, 2020

Update: Watermain Extension for Selous Creek

October 23 2020

Installation of the watermain along the Great Northern Trail (GNT) and along the Hoover Street Right-of-Way is now complete. The final tie-in and pipe reconfiguring will take place next week (October 26-30) at the top of Stanley Street.  Hydrosee...

Read on...

City Project Gallery
Posted on: October 16, 2020

Update: Watermain Extension for Selous Creek

2020-07-10 07.20.13

The Great Northern Trail will be closed north of the Mountain Station Parking Lot to the Hoover Street Right-of-Way on Monday, Oct 19th and Tuesday, Oct 20th to complete a water tie-in to the existing lines as part of the watermain extension for Selous Cr...
Read on...

City Project Gallery
Posted on: October 9, 2020

Update: Watermain Extension for Selous Creek

IMG_0566

Installation of the watermain along the Great Northern Trail and along the Hoover Street Right-of-Way is nearing completion. Next week the  Kays Contracting crews will install test points at either end of the line and commence to fill the line wi...

Read on...

City Project Gallery
Posted on: October 2, 2020

Update: Watermain Extension for Selous Creek

Over the next couple of weeks, the Kays Contracting crews will continue to work toward Mountain Station reservoir along the Hoover Street Right-of-Way. Other than the immediate residents,  little disruption is anticipated.  The works on ...

Read on...

City Project Gallery
Posted on: September 25, 2020

Update: Watermain Extension for Selous Creek

September 25 2020

From September 8th through September 18th, Kays Road Contracting Ltd. crossed the Great Northern Trail at the Hoover Street Right-of-Way (ROW) and extended the watermain along the steep slope above the old rail grade. A repetitive dull thudding sound, hea...

Read on...

City Project Gallery
Posted on: August 21, 2020

Update: Watermain Extension for Selous Creek

August 21 2020 2

The prime contractor for the Selous Creek watermain extension project, Kays Road Contracting Ltd. has been working at installing water lines in and around the Mountain Station reservoir site for the past month. Contractually this work needs to be complete...

Read on...

City Project Gallery
Posted on: December 1, 2017

December 1, 2017 - UPDATE #10 - Hall Street Project - Phase II

10_HallStreetProgressUpdate

Click here to read the latest update on the Hall Street Project for the week of November 27th, 2017.

Read on...

City Project Gallery
Posted on: November 24, 2017

November 24, 2017 - UPDATE #9 - Hall Street Project - Phase II

9_HallStreetProgressUpdate

Click here to read the latest update on the Hall Street Project for the week of November 20th, 2017.

Placing Pipe during Phase II construction.

Read on...

City Project Gallery