As the snow settles over the Pier worksite and we head in to the holidays, North Mountain Construction has cleaned up the worksite at the bottom of Hall Street and demobilized for a winter site closure.
While you may see some decking work still being compl...
You may have noticed a GWIL crane on the construction site in the last week. The crane is assisting in the install of the steel beams on the steel pilings.
MarWest recently completed the install of the storm sewer tie-in with the City storm line....
Here is the latest Pier Project update for the week of August 22, 2022
In early August, North Mountain Construction poured concrete in the Ladybird display building walls and strip footings.
Here is the Ladybird display building walls and footings...
Graham Marine continued installing the pilings. They have now demobilized from the site, leaving one barge for the welder to continue work.
The site for the Ladybird display building was prepared and the concrete footings were placed.
The rebar an...
Work at the pier has continued to progress steadily since the last project update. Graham Marine has finished the pier deconstruction and has removed the existing piles:
Photo showing pier deconstruction.
Photo showing pile removal.
Work has starte...
The project replacement project is underway with site works proceeding last week. The site and laydown area has been fenced and the work trailer is present on site. Please observe all construction signage when travelling adjacent to th...
May 13, 2022
Nelson, BC - The City has been working to create opportunities to improve the current City pier, located at the foot of Hall Street and the waterfront. It was identified several years ago that t...