Pier Project update for June 2023
Summer is almost here and we are seeing great changes down at the Hall Street Pier. Pictures paint a 1000 words but stop by and take a look next time you are down by the waterfront.
All of the deck boards and wooden handrails have been installed. The floating docks below the pier have been put in place.

A new access gate to the float plane dock is now installed which includes a new gangway down to the dock.

Float plane gangway ramp bolts were installed and secured and the float plane dock was cleaned.

The Ladybird display building has the interior decking installed along with the air handling unit. The roof flashing was also completed.

Landscaping and sprinkler installation by City of Nelson parks staff.

What a beautiful view of the Pier from the water.....

Work being completed currently:
- MarTech Electric to continue fixing lighting at the benches & bumpers.
- City of Nelson parks staff to continue landscaping and sprinkler installation.
- North Mountain to install wood nailers and decking to floating dock gangway ramps.
Contractors on site:
North Mountain Construction, True Mechanical Engineering, MarTech Motor Winding, MarTech Electric, Heritage Roofing, Graham Marine and City of Nelson Staff.